What is the 94% Unit Learning Curve?

terpmom
New Member

It took a contractor 5000 hours ot manufacture their first unit of an item. If the contractor expects to achieve a 94% unit learning curve, how many hours would be required to manufacture units 76-100?

Tags (1)
0 Karma

lukejadamec
Super Champion

7500 hours