Hi,

We have a tier related to a java process. The point is that this tier is related to a batch process. However, it is recognized as a normal process and it is not unregistered after a time although it finished its function time before.

So, is there any way to control the time in which a node can be unregistered automatically if it doesn't have any traffic for a time?

Thanks,

Carlos

Labels (1)
Tags (2)
0 Karma
1 Solution

Hirokazu_Mori1
Path Finder

Thank you for your reply!

A suitable retention period value depends on your requirement.
What I can say is if your process works periodically and you would like to delete a node to the process during waiting time to the next, a retention period must be smaller than that repeating period, otherwise the node will stay on the controller UI.
A retention period is the elapsed time after a node loses a connection to a process, no data transfer happens or a JVM is shutdown.
Therefore I guess a retention period setting will work well as long as no data transfer happens.

And "-Dappdynamics.jvm.shutdown.mark.node.as.historical=true" only works after a JVM shutdown.
This makes a node historical and the node will disappear soon after a JVM shutdown. 

I hope this answer can help you.


Best regards,

Hirokazu

View solution in original post

Carlos_Ortega
Explorer

thank!

0 Karma

Hirokazu_Mori1
Path Finder

Hi @Carlos.Ortega,

 

Thank you for your post to the community!

 

The AppDynamics provides Node Activity Settings.

In the settings, a retention period setting will match your request. It defines how long Nodes are kept on the Controller UI after finishing.

You can set a small value to the retention period.

Or you can also use ‘-Dappdynamics.jvm.shutdown.mark.node.as.historical=true’ property which marks node historical at JVM shutdown.

 

I hope this document below will help you well.

https://docs.appdynamics.com/22.6/en/application-monitoring/administer-app-server-agents/historical-...

 

Best regards,

 

Hirokazu

Carlos_Ortega
Explorer

Hi @Hirokazu.Mori,

thanks for your answer. Can you recommend to me some values for the time retention period, please?

also, using "-Dappdynamics.jvm.shutdown.mark.node.as.historical=true", Are going to be disconnected the agents after being used? We have a point that these nodes are connected but they did their function and after it, they are connected for some time instead of being unregistered.

thanks

0 Karma

Hirokazu_Mori1
Path Finder

Thank you for your reply!

A suitable retention period value depends on your requirement.
What I can say is if your process works periodically and you would like to delete a node to the process during waiting time to the next, a retention period must be smaller than that repeating period, otherwise the node will stay on the controller UI.
A retention period is the elapsed time after a node loses a connection to a process, no data transfer happens or a JVM is shutdown.
Therefore I guess a retention period setting will work well as long as no data transfer happens.

And "-Dappdynamics.jvm.shutdown.mark.node.as.historical=true" only works after a JVM shutdown.
This makes a node historical and the node will disappear soon after a JVM shutdown. 

I hope this answer can help you.


Best regards,

Hirokazu
Career Survey
First 500 qualified respondents will receive a $20 gift card! Tell us about your professional Splunk journey.
Get Updates on the Splunk Community!

.conf25 Global Broadcast: Don’t Miss a Moment

Hello Splunkers, .conf25 is only a click away.  Not able to make it to .conf25 in person? No worries, you can ...

Observe and Secure All Apps with Splunk

 Join Us for Our Next Tech Talk: Observe and Secure All Apps with SplunkAs organizations continue to innovate ...

What's New in Splunk Observability - August 2025

What's New We are excited to announce the latest enhancements to Splunk Observability Cloud as well as what is ...